Construction Projects

Construction Projects

2016
Construction Projects

East Loveland Nature Preserve Pedestrian Bridge– The City of Loveland was awarded an 80% matching grant, up to $80,000 of a $100,000 cost, with federal funds from the Recreational Trails Program being administered through ODNR for the installation of a new pedestrian bridge from the parking lot at 227 East Loveland Avenue over Bares Run creek to improve public access into the East Loveland Nature Preserve.  Choice One Engineering completed the site surveying and design.  Sunesis Construction completed the construction in early 2016.

 

Downtown Traffic Signal Improvements- The City of Loveland has budgeted $119,500 for an overall engineering study and construction improvements to the traffic signals in downtown Loveland for 2016.  The three intersections (SR 48 at Broadway, SR 48 at W. Loveland, and W. Loveland at Karl Brown) have received radar vehicular detection capability as well as pedestrian push-buttons, as needed.  Capital Electric performed the initial installation and is in the process of refining the settings of the radar detection equipment.

 

McCoy Trail Spur and Parking Lot– The City of Loveland and the State of Ohio through ODNR are funding the development of City-owned property south of Broadway Street.  The project scope includes construction of a parking lot, pedestrian connections to the Little Miami Scenic Trail, storm water quality treatment and detention, landscaping, lighting, and associated work.  Surveying and design were completed by Choice One Engineering.  J.K. Meurer was the low bidder of the construction contract.  Construction began in October, 2015, was on a hiatus over the winter, and was completed in spring of 2016.

 

East Loveland Avenue Sidewalk Extension-  The project includes the installation of approx. 440 linear feet of sidewalks along the north side of East Loveland Avenue from 209 East Loveland to the Moose Lodge Building. The project will provide pedestrian connectivity between the public parking lot, other site amenities and adjacent Nature Preserve to the historic downtown area.  Choice One Engineering Corp. has completed the survey and design.  Earth & Pipe Contracting was the low bidder awarded the construction contract.  Construction was completed in July, 2016.

 

Nisbet Park Picnic Shelter Improvements– The City of Loveland received a $19,050 Nature Works grant from ODNR, and will provide a local match for improvements at Nisbet Park at the north end of Karl Brown Way.  The project will include improvements to an existing picnic shelter, including replacement of the concrete foundation and installation of gutters and downspouts.  The grant will also help pay for new picnic tables and grills.  The construction by Koch Construction was completed in spring, 2016.

 

Annual Street Project– The annual street program was budgeted to have only $301,121 in 2016, less than half of what is needed to maintain the City’s streets on a 15-year repaving cycle. J.K. Meurer was the low bidder of the construction contract.  The roadways planned for resurfacing, which make up just over 3% of the City’s public pavements, include Bird Dog Ct., Cross Alley, Lebanon Rd. (from W. Loveland Ave. to City’s North Corporation Limit), Lindenhall Dr., Lycoming St., Rutgers Ct., Wilmington Dr, and a segment of Albright Dr.  The work on these streets has been completed and there are minor remaining funds that will be applied toward repairs and repaving of a segment of Brandenberg Drive.  Limited concrete curb replacements on Brandenberg are scheduled to begin the week of Sept. 6, weather dependent.  Depending on the cost of curb replacement and remaining fund balance, Brandenberg may be repaved from Stockton to Wittenberg.

 

East Loveland Parking Lot Resurfacing & Expansion–  The project includes the resurfacing of the existing parking lot and an addition of approximately 16′ of pavement along the rear side of the parking lot, restriping, & signage replacement.  The project site is between 227 East Loveland Avenue and the nature Preserve.  The project is expected to have a bid opening and award in August, with construction completely in fall, 2016.

 

For more information about these projects and others in Loveland, contact Cindy Klopfenstein, PE, City Engineer, at 683-1050 or CKlopfenstein@lovelandoh.com.