Construction Projects

Construction Projects

New 1 MG Water Tower- Installation of a proposed 1 MG elevated water storage tank near the existing tank at Commerce Park is currently under design.  The bid opening is anticipated to be held in spring of 2013, with construction completed by the end of 2013.  After it is in service, the existing 0.5 MG water tower at Commerce Park will then be repainted (inside & out) in spring of 2014.                               

Booster Pump Station- Installation of a proposed booster pump station at Boike Park is currently under design.  The bid opening is anticipated to be held in spring of 2013, with construction completed by the end of 2013.     

Fallis Rd Water Line Replacement- The project involves water line replacements and repaving on Fallis Rd. from Betty Ray Dr. to Rich Rd.  The City is receiving a 0% interest loan from OPWC for the approximately $618,200 construction cost.  The construction project is currently under design and construction is expected to start as early as mid-July, 2012. The City of Loveland will be holding an Open House at City Hall, 120 W. Loveland Avenue on Wed., May 30, 2012 at 7:00 PM to discuss the City’s plans and answer questions about the project. 

Park, Elm, & Centre Water Line Replacement- The project involves water line replacements, some storm sewer work, and repaving on Park Ave., Elm St., and Center St.  The City is receiving a 0% interest loan from OPWC for the approximately $478,500 construction cost.  The construction project is currently under design and construction is expected to start as early as mid-July, 2012. The City of Loveland will be holding an Open House at City Hall, 120 W. Loveland Avenue on Wed., May 30, 2012 at 7:00 PM to discuss the City’s plans and answer questions about the project. 

SR 48 Repaving- The City of Loveland and the Ohio Department of Transportation are jointly participating in repaving 0.42 miles of State Route 48 from Loveland-Miamiville Rd. to west of Founder’s Dr.  The contribution from ODOT is estimated at $71,000 of the approximately $123,000 project cost.  Barrett Paving was the low bidder and anticipates paving work to last through the week of June 15, 2012, dependent on weather.

 2012 Road Program- The 2012 road maintenance program is anticipated to start after June 15, 2012.  The program will begin with crack-sealing repairs, then milling and paving or Black mat installation.  The work will be completed by August 24th,weather-dependent.  On-street parking will be temporarily restricted, but traffic will be minimally impacted by these repairs.

The following roads are scheduled for repair or resurfacing in 2012:

Street (From/To Limits if not All) Scope
Cherokee (W Main to Sunrise) Mill & Pave
Pueblo Ct Mill & Pave
Sioux Dr (Tuscarora to W Main) Mill & Pave
Oneida (Tuscarora to W Main) Mill & Pave
Apache Ct Mill & Pave
Seminole Dr (W Main to Tuscarora) Mill & Pave
Sunrise Dr. Black Mat
W Main St (Cherokee to W Term) Black Mat
Potomac Ct. Black Mat
Bellwood Dr (Sunrise to Term) Black Mat
Quailwoods (Dogwood to Tanglewood) Mill & Pave
Oak Canyon (Quailwoods to Pheasant Hills) Mill & Pave
Fawn Ct Black Mat
W Loveland Av (Pheasant Lake to W City Limit) Limited Repair
S Lebanon Rd (Loveland Madeira Rd to W Loveland) Limited Polyfil Repair
Paxton Rd (bend) Limited Polyfil Repair
Bridle/Stirrup/Saddleback Limited Repair
Fifth St. (E. Loveland to Term) Mill & Pave
Union & First Streets Mill & Pave
Bishop Plc. Black Mat
State Route 48 (Love.-Miami. to just west of Founder’s) Mill & Pave

 Strawser Construction was the low bidder and awarded the contract for the City’s 2011-2012road program.  Strawser Construction was also the contractor for the 2009-2010 road rehabilitation projects.  They will give residents, living on streets receiving the surface treatment, notice the night before the work will be done so they can make necessary arrangements for alternative parking and ingress/egress. 

 Annual Sidewalk Program- Innovative Concrete and Utility Construction, LLC was the low bidder for the 2012 Sidewalk Replacement Program.  They began the first phase of construction in May, 2012 on Broadway St., Third St., O’Bannon Av., East and West Loveland Ave. from the East Corp. limit to Loveland-Madeira Rd., Karl Brown Wy., Hanna Av., and State Route 48.  The Contractor will return in June, 2012 to complete sidewalk replacements for any other property owners who have signed up for the City’s sidewalk and driveway apron replacement program and not had their work completed in the first phase, as well as anyone who did not comply with an order to satisfactorily correct their sidewalks by a June 22, 2012 deadline.  Maintenance inspections on existing sidewalk and driveway apron conditions will be performed in the fall of 2012 for E. Main St., Elm St., Chestnut St., Wall St., Riverside Dr., Park Ave., Centre St., and W. Loveland Ave. from Loveland-Madeira Rd. to the west Corp. limit.

 

If you have any questions or comments regarding these projects, please contact the City Engineer, Cindy Klopfenstein, PE, CFM at 513-683-0150 or CKlopfenstein@lovelandoh.com.